Programme |
PTCRRMP |
PTCRRMP |
PTLivSPP |
PTLivSPP |
| Loan number |
664-LK |
693-LK |
694-LK |
665-LK |
| Signed date of Loan Agreement |
01-12-2005 |
18-04-2008 |
18-04-2008 |
01-12-2005 |
| Effective date |
16-10-2006 |
18-09-2008 |
18-09-2008 |
09-03-2006 |
| Program Completion date |
31-12-2011 |
30-09-2013 |
30-09-2011 |
31-03-2009 |
| Loan Closing date |
30-06-2012 |
31-03-2014 |
31-03-2012 |
30-09-2009 |
| Loan Amount-SDR
( Special drawing Rights ) |
9,400,000
| 10,950,000
|
1,650,000
|
1,560,000 |
| Loan amount –US$ |
14,201,802 |
15,713,578 |
2,367,800 |
2,356,985 |
Programme vise total Loan amounts in US$ |
|
|
|
|
| |
| |
Programme Components
|
|
Financial Allocations (US$) |
A. Coastal Habitat and Resource Management
-Information dissemination and Awareness Programmes (By CCD)
- Fishery Management Plan-NARA & DFAR
- Stock Assessment-NARA
-Dune Restoration*
- Mangrove Restoration-CCD
- Water Quality Monitoring-CCD
*Deleted at the IFAD Direct Mission and signed Aide Memoir -2008 August and added to Component B |
194150
436870
388320
-----
179610 388350
|
1,587,300 |
B. Support to Artisanal Fisheries
- Post-tsunami Recovery
- Fishery Production Development
- Post-Harvest and -Marketing Development
- New works (Agreed on Aide Memoir-August 2008 by suppressing sand dune restoration of component A and certain works in the component B ) |
5,169,900 10,321,200 1,541,600 2309200 |
19341900 |
C. Micro-Enterprise and Financial Services
-Support to Micro Enterprises
-Financial Services Development |
1,080,500 1,592,100 |
2,672,600 |
D. Social and Economic Infrastructure |
|
7,200,000
|
E Gender, Policy Support and Programme Management |
|
3,249,200
|
Total Programme Cost
-Total base line Cost (Total of Component A to E)
|
|
34051000
|
| |
| -Physical Contingencies |
2,070,100 |
| -Price Contingencies |
4,226,300 |
-Total Programme cost |
40347400 |
|
|
| |
Major Development Activities of the Programmes (Over Rs. 10 Million)
Under the Three Year Rolling Plan 2009-2011
|
|
| |